We know when you've got a project underway, you want to see progress. However, it might not always be feasible to drive out to the job site everyday. We have the solution. This section will be regularly updated with photos as we progress on various projects. We'll also let you know when something new or exciting comes across our desk. So pour yourself a cup of coffee, pull up a chair, and click around. Its our way of assuring our clients that we're working hard for you.


Norway Savings Bank Branch .. Gray, Maine September 22, 2014

Wall & Soffit Framing

Wall & Soffit Framing

With the exterior siding and trim almost complete, the focus now lands on site, granite curbing, concrete walks, pylon sign structure, and yes, CMP did their thing to establish elevated service over the roadway!

It's going down! or is that up?

It’s going down! or is that up?

What a pretty day it was indeed!  Hung hollow metal egress doors, began drive through trim, finished ceilings, installing pneumatic tube system in canopy, we got a lot done since our last report!

Shingles and Lead Coated Copper Complete

Shingles and Lead Coated Copper Complete

IMG_1570  Interior framing completed, drywall hung, drywall finish began .. Looking good!

IMG_1571  Mechanical duct work and unit piping, insulation, data pre-wire .. and the local CEO closed in.

IMG_1579  Establishing planter islands, tie in of cooling units, prep for concrete sidewalks.

Granite Continues

Granite Continues

Drivethru Column Framing North Building Corner Gray's "Twin Towers"

Drivethru column framing, trim, and siding will be complete today.

Placing Curb around building.

Placing Curb around building.





Norway Savings Bank Gray ~ Project Progress 8.29.14

Another incredible Friday here in beautiful downtown Gray Maine .. this week has been really productive!  We had our bi-weekly project meeting with the Owner and Architect and specialty subs and consultants, and met one major milestone.  We finished the ‘off-site’ work in the adjacent roadway intersection of Libby Hill Road and Rt.26, we began roofing, including integral lead coated copper gutters, we are well underway on the interior, with roughin and spray foam in exterior walls……continuing siding and trim.  We also flew the cupola, building it on the ground for safety-sake.  Check out our progress pics for this week!

Front Corner Dormer

 

Set the cupola this week, continued LCC roof accessories.

Libby Hill Road Off-site Scope Complete

Libby Hill Road Off-site Scope Complete

Spray Foam Interior Building Rear Siding/Trim IMG_1551

Interior thermal barrier placement .. 4″ average of spray foam .. Drivethru side siding and trim .. cement clapboards it is!

 

 

 

 

 

Roof Shingles

Certainteed architectural roof shingles, lead-coated aprons, integral gutters, base and step flashings it is!

Spray foam technology

Spray foam technology

Bios Environmental setting up to spray .. quite a technical application .. generated a LOT of heat during the spray process!

 





Norway Savings Bank Branch Progress ~ Gray, Maine ~ August 22, 2014

Entry Porch Slab Placement

Front Entry Concrete Slab Placement

Air barrier roof-ready trim begins

Air barrier roof-ready trim begins

Air barrier continues

Air Barrier Continues

IMG_1401

Interior Wall Framing Begins

South Gable Complete

South Gable Siding & Trim Complete

Interior framing IMG_1402 Siding & trim Cupola Roof Off-site Road Scope South Gable Siding South Gable Siding Shingles MEP Rough HVAC Units North Gable Trim Starts HVAC Unit Install Drive Thru Island Bollards Drive Thru Island Concrete Placement

 

Progress for the end of July and to the third week in August has proven quite productive.  Onsite grading and base course paving; siding and trim began, and lots of headway on the interior roughin and framing.  The off-site road work is progressing well, with a due/completion date of August 27th….the buses roll and kids start school next week!  We are on our way and on schedule for the Mid-November Substantial Completion!  I love this part of the project!





Norway Savings Bank Branch ~ Gray, Maine ~ July 24, 2014 Progress

Roof Sheathing Continues

Roof Sheathing Continues

Beginning of Dormer

Beginning of Dormer

Ongoing Shell

Ongoing Shell

Roof Sheathing Done Safe

Roof Sheathing Done Safe

Pick that Dormer!

Pick that Dormer!

Pick Second

Pick Second

Began Off-site Scope

Began Off-site Scope

IMG_1335

Window Bucks

Window Bucks

IMG_1339

Drivethru Canopy

Drivethru Canopy

Integral Gutter Roofline

Integral Gutter Roofline

IMG_1353

"No .. it goes like THIS!"

“No .. it goes like THIS!”

"Like THIS Bruce?"

“Like THIS Bruce?”

IMG_1367

Let the BLUE begin!

Soffits Begin for Roof-Ready

Soffits Begin for Roof-Ready

Windows & Air Barrier

Windows & Air Barrier

The last two weeks in Maine have been hot and sticky .. NOT complaining mind you .. but in spite of that, construction in summer still has it’s benefits! Dry, humid, almost 100 degrees, no shade .. we’ve seen it all.  But in spite of all of that, our crews have hung tough and progress is outlined in the following pictures.  Enjoy seeing our progress .. we are on task and schedule!





Progress Pics Norway Savings Bank ~ 1 Libby Hill Rd. , Gray, Maine

As with any project, there are critical path moments in time, that tend to make progress look good!  This is one of those weeks for this one!  Panels are by Porter Building Systems .. Installation is by Veterans Construction .. Art Caron’s crew.  Checkit out!

Setting the last gable

Prepping the last gable

IMG_1292

IMG_1290

Adding bearing clips for entry beams

Adding bearing clips for entry beams

Truss Pick Day

Truss Pick Day

IMG_1306





Perspective Project featured in Hancock Lumber Ad

We were recently honored to have our Falmouth Norway Savings Bank project featured prominently in an ad for Hancock Lumber and Eagle Windows. Check it out!

Hancock Lumber and Eagle Windows Ad