With the exterior siding and trim almost complete, the focus now lands on site, granite curbing, concrete walks, pylon sign structure, and yes, CMP did their thing to establish elevated service over the roadway!
What a pretty day it was indeed! Hung hollow metal egress doors, began drive through trim, finished ceilings, installing pneumatic tube system in canopy, we got a lot done since our last report!
Interior framing completed, drywall hung, drywall finish began .. Looking good!
Mechanical duct work and unit piping, insulation, data pre-wire .. and the local CEO closed in.
Establishing planter islands, tie in of cooling units, prep for concrete sidewalks.
Drivethru column framing, trim, and siding will be complete today.