We know when you've got a project underway, you want to see progress. However, it might not always be feasible to drive out to the job site everyday. We have the solution. This section will be regularly updated with photos as we progress on various projects. We'll also let you know when something new or exciting comes across our desk. So pour yourself a cup of coffee, pull up a chair, and click around. Its our way of assuring our clients that we're working hard for you.


Norway Savings Bank Gray ~ Project Progress 8.29.14

Another incredible Friday here in beautiful downtown Gray Maine .. this week has been really productive!  We had our bi-weekly project meeting with the Owner and Architect and specialty subs and consultants, and met one major milestone.  We finished the ‘off-site’ work in the adjacent roadway intersection of Libby Hill Road and Rt.26, we began roofing, including integral lead coated copper gutters, we are well underway on the interior, with roughin and spray foam in exterior walls……continuing siding and trim.  We also flew the cupola, building it on the ground for safety-sake.  Check out our progress pics for this week!

Front Corner Dormer

 

Set the cupola this week, continued LCC roof accessories.

Libby Hill Road Off-site Scope Complete

Libby Hill Road Off-site Scope Complete

Spray Foam Interior Building Rear Siding/Trim IMG_1551

Interior thermal barrier placement .. 4″ average of spray foam .. Drivethru side siding and trim .. cement clapboards it is!

 

 

 

 

 

Roof Shingles

Certainteed architectural roof shingles, lead-coated aprons, integral gutters, base and step flashings it is!

Spray foam technology

Spray foam technology

Bios Environmental setting up to spray .. quite a technical application .. generated a LOT of heat during the spray process!

 





Norway Savings Bank Branch Progress ~ Gray, Maine ~ August 22, 2014

Entry Porch Slab Placement

Front Entry Concrete Slab Placement

Air barrier roof-ready trim begins

Air barrier roof-ready trim begins

Air barrier continues

Air Barrier Continues

IMG_1401

Interior Wall Framing Begins

South Gable Complete

South Gable Siding & Trim Complete

Interior framing IMG_1402 Siding & trim Cupola Roof Off-site Road Scope South Gable Siding South Gable Siding Shingles MEP Rough HVAC Units North Gable Trim Starts HVAC Unit Install Drive Thru Island Bollards Drive Thru Island Concrete Placement

 

Progress for the end of July and to the third week in August has proven quite productive.  Onsite grading and base course paving; siding and trim began, and lots of headway on the interior roughin and framing.  The off-site road work is progressing well, with a due/completion date of August 27th….the buses roll and kids start school next week!  We are on our way and on schedule for the Mid-November Substantial Completion!  I love this part of the project!